Two Town of Greeneville improvement projects were completed this week.
TOWN HALL
Skyline Restoration completed repair of columns, portico and windows at Greeneville Town Hall, including additional improvements added after the original contract was approved.

STREET PAVING
The long awaited TDOT paving schedule for portions of three Greeneville streets was completed when paving and striping on East Church from Bernard Avenue to near Stratford Drive was finished.


In October, Summers-Taylor paved a segment of Erwin Highway from 11E to the Greeneville and Tusculum city-limit line, then a segment of Old Shiloh Road from Old Tusculum Road to Shiloh Road.