After setting different estimated dates for completing repairs on the 11E bridge over Snapps Ferry Road, including recently releasing no completion date, the Tennessee Department of Transportation is now expecting to complete the project this fall.
An additional traffic lane shift is also to be expected before the project is complete.
Work on the bridge has been ongoing for months after beginning in January, and the repairs have taken much longer than anticipated.
While repairs on the bridge deck were expected to be completed by the end of April, a TDOT representative said in late April that work on the deck would extend into May.
The “contract completion date” for the entire repair project, not just the deck, was originally set for June 15. At one point recently, no completion date was provided for the project.
One lane of traffic has been closed on each side of the bridge since the project began in January. The closure has led to traffic delays in the area since the repairs started.
Additionally, the on ramp from Snapps Ferry to Southbound 11E has been closed during the repair process.
Greeneville Mayor Cal Doty contacted TDOT last week for more information on the project, and a TDOT representative told him that additional issues with the bridge were discovered during the repair process which has prolonged the project. The continued work on the bridge will require another traffic lane shift on the bridge.
Doty received the following email from a TDOT representative.
“During the repair work, unsuitable material was discovered that had not been previously identified. In order to remove and repair the defective concrete, one more traffic shift will be necessary in the next few weeks. In addition to the additional work previously mentioned, the contractor will still need to paint both bridges and install railroad protective fencing on top of the parapet walls, but that work should not take an extensive period.,” the email said. “We currently anticipate this project being completed this Fall, and will provide updates as they are known.”
Work being down on the bridge includes concrete deck repair and some substructure repairs according to TDOT. In addition, epoxy, paint, asphalt, and striping will be applied during the project.
It has appeared to many in the local community that work on the bridge has slowed or ceased in recent weeks, however, TDOT Region 1 Communications Officer Mark Nagi said in a recent email that epoxy injection is underway.
Nagi said that the barriers will remain in place while the project is ongoing, even if motorists may not see workers at the site each day.
“Currently the lane closure is still serving as a barrier for workers performing epoxy injection into the bridge structure. This is not a construction activity where motorists would potentially see workers performing the injection day in and day out, but the barriers are still needed for the instances when workers are present performing the injection,” Nagi said.
Motorists should exercise increased caution when traveling through the area while workers are present.