The TDOT paving schedule on Main Street in Greeneville continues this week. The contractor brought a second milling machine to expedite the work last week.
Today, milling and paving from 11E to near the SR350 Intersection will be continuing. As per the current schedule, no work is scheduled Tuesday or Wednesday. Milling and paving south bound SR 35 from near the SR 350 intersection to Ricker Avenue will be conducted on Thursday and Friday. TDOT reports Monday thru Wednesday , September 22-24 will be for paving of Main Street if any of the mainline remains. Also side roads will be paved those days next week.